A project team is prioritizing the creation of project artifacts and enforcing it rigidly, while they face issues with delays in deliverables. How should the project manager respond?

الخيارات

  • A Facilitate the implementation of an automated tool for the team to manage project artifacts.
  • B Advise the team that solely focusing on artifacts will not produce successful project deliverables.
  • C Implement stricter controls so that project artifact creation is given the utmost importance.
  • D Recognize the team's efforts for documenting artifacts and motivate them with an incentive mechanism.