اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 771 من 874

كل الأسئلة

A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead. The requested workaround will introduce delays and require additional budget.
What should the project manager do?

الخيارات

  • A Mitigate risks associated with the workaround to avoid project delays.
  • B Request to use the management reserve to keep the schedule.
  • C Discuss the options with the client as part of the change control process.
  • D Proceed with the approved risk response plan.