اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 772 من 874

كل الأسئلة

During the execution of a project, a key stakeholder complains to the project manager about recent communications. The key stakeholder explains that the relevant information from the project team was incomplete and late. As a result, the key stakeholder is beginning to disengage from the project.
What should the project manager do?

الخيارات

  • A Send relevant information to all key stakeholders simultaneously to ensure consistent communication.
  • B Ask the project sponsor to hold a meeting with the key stakeholder to ensure that the stakeholder is engaged in the project.
  • C Update the communications management plan to fulfill the key stakeholder's expectations about relevant information.
  • D Explain to the key stakeholder the way in which the project team communicates information.

النقاشات