During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule.
What should the project manager do first?

الخيارات

  • A Add the risk and the delay to the risk register.
  • B Update the schedule to include the delay.
  • C Update the issue log and act to minimize the impact.
  • D Escalate to the management team for delay approval.