An agile project team is looking to develop quality standards for a project. How should the project manager coach the team?

الخيارات

  • A Determine the tools and techniques suitable for the project and ensure that testing is done early and continuously.
  • B Inform the team that user acceptance testing is required to ensure that the product owner accepts the solution.
  • C Ensure that the definition of done (DoD) is provided when the product owner agrees that all acceptance criteria have been met for the user story.
  • D Insist that test-driven development is implemented along with the automated testing.