A project manager schedules virtual daily standup meetings for a project, but half of the team members regularly join late or miss the meeting altogether. What should the project manager do?

الخيارات

  • A Use one-to-one virtual meetings because they are more efficient.
  • B Agree on a new time and reschedule the daily standups.
  • C Discuss ground rules with the team that will include daily meetings.
  • D Ask senior management for coaching regarding this situation.