اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 757 من 874

كل الأسئلة

A project sponsor asks the project team to add an enhancement to the project. How should the project manager address this request?

الخيارات

  • A Check if the budget can cover the enhancement.
  • B Accept the request because it came from the project sponsor.
  • C Validate the proposed change's impact on the project.
  • D Refuse the project sponsor's request because it is out of scope.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.