اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 736 من 874

كل الأسئلة

A project manager will meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks with external dependencies was delayed by one week. The project manager knows this will have an impact but does not know the exact details.
What two actions should the project manager take? (Choose 2)

الخيارات

  • A Wait for the client to raise a concern and collect more information.
  • B Review the lessons learned from similar past projects.
  • C Update the risk log and bring this up in the meeting with the client.
  • D Gather additional information and estimate the impact.
  • E Discuss the issue with the external supplier's authority.