اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 737 من 874

كل الأسئلة

During a scope validation exercise toward the end of a project, a project manager realizes that some operational project requirements were not captured in the project scope of work. Although completing these items will have an impact on the project’s completion date, it will increase the likelihood of customer acceptance.
What should the project manager do to address the issue?

الخيارات

  • A Issue a change request to include the additional scope, and track the completion of the work items.
  • B Document the issue in the lessons learned document, and discuss this with the project sponsor.
  • C Issue a change request to remove items from the scope of work and keep the project on schedule.
  • D Arrange to pass the cost to the operational area since the customer will benefit.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.