The team’s work assignments have been generically distributed. A new team member is performing slower than expected.
What should the project manager do?

الخيارات

  • A Extend the project timeline to allow the new team member to work at their own pace.
  • B Have all of the other team members retrain the new team member to improve team performance.
  • C Assess the new team member’s skills in order to determine additional training needs.
  • D Change the way the work assignments are distributed to facilitate new team member development.