During a progress review meeting, the project sponsor requests a complete revamp of the product roadmap to meet the strategic objectives based on market conditions. This change will result in a completely new product.
What should the project manager do first?

الخيارات

  • A Discuss with the team and implement the revisions that were requested by the sponsor.
  • B Perform a root cause analysis to assess which deliverables can be reused by the team.
  • C Update the business case and seek sponsor approval on the modified project scope.
  • D Put the current project work on hold and revisit the scope based on the impacts.