During a daily meeting of a challenging project, two team members started to argue on the preferred solution based on their assumptions. The situation prevented the progress to the next phase of development, which could impact the finish date of the project.
What should the project manager do next?

الخيارات

  • A Ask the human resources (HR) department to replace the team members.
  • B Divide the team into small groups to avoid future arguments and delays.
  • C Meet with the team members to discuss the priority of the project schedule.
  • D Make a decision based upon the project manager’s knowledge and expertise.