A project manager is finalizing the project charter and has invited the project sponsor and key stakeholders to confirm the project estimates. The project manager suggests adding a budget reserve to meet unforeseen risks, but the project sponsor disagrees.
What should the project manager do?

الخيارات

  • A Demonstrate that risky projects are subject to change so adding reserves to the budget is a necessity.
  • B Explain to the project sponsor and key stakeholders the need to add the reserve and get their buy-in.
  • C Seek key stakeholders' approval and finalize the budget with the reserve.
  • D Agree with the project sponsor and finalize the budget without the reserve.