A project manager is developing the project schedule with the project team. The team members estimate that an optimistic duration is 5 days, the pessimistic duration is 20 days, and the most likely duration is 11 days.
What duration should the project manager use?

الخيارات

  • A 11 days
  • B 12.5 days
  • C 11.5 days
  • D 12 days