A transformation project that is composed of agile streams has come to an end. How should the project manager collect the experience gained during this project?

الخيارات

  • A Organize a lessons learned session with the team.
  • B Ask for feedback during the next standup meeting.
  • C Create a document with the information from the last sprint retrospective.
  • D Conduct a session with the members of the project steering committee.