The team’s velocity is inconsistent, leading the product owner to believe the team is creating too many points in their user stories. What should the scrum master do first?

الخيارات

  • A Raise this concern with the team and review the performance of the past three sprints.
  • B Meet with the product owner for planning and to resize the stories in the backlog.
  • C Remind the product owner that their role is to determine what the team should work on during the iteration.
  • D Invite the product owner to planning poker meetings and get their approval after each story is sized.