A project is 20% complete. The client has accepted a project order amendment that involves a major change. Without this major change, the project result will be useless for the client organization.
What should the project manager do?

الخيارات

  • A Set up a meeting with the client and the project team to identify ways to safeguard the project from the change.
  • B Consult the project sponsor to understand if the change must be processed for project execution.
  • C Update the project status from "active" to "on hold" until there is more clarity on the scope of the change.
  • D Initiate planning for the project with the modified scope as laid out in the client’s purchase order.