An organization with a new project management office (PMO) team is now undergoing a restructuring. Additionally, there is a lack of communication from the PMO to the team members.
How should the project manager handle this situation?

الخيارات

  • A Set up a meeting with the PMO and project team to discuss and clarify questions related to restructuring.
  • B Meet the PMO team and explain the importance of communicating with the team members for project success.
  • C Inform the team that despite the new PMO and restructuring, the team will not change.
  • D Request the PMO team share updates on the restructuring with the team members on an immediate basis.