A team member mentions to the scrum master that the user stories are too long. The team member believes this may be the cause of the team’s inability to deliver value for stakeholders.
What should the scrum master do?

الخيارات

  • A Review the user stories with the stakeholders and ask the product owner to break them down into more manageable units.
  • B Ask the team member to suggest using shorter user stories to the product owner so that the next sprint can move faster.
  • C Review the user stories with the team and ask the product owner to break them down into more manageable units.
  • D Ask all the team members for their views about using shorter user stories so that value can be created for stakeholders.