In a fixed-budget project, the team has received a prioritized list of requirements and has nearly completed the first iteration. The CEO has decided to redirect the team to focus on creating a presentation for their upcoming technology summit. The CEO is not flexible about this request.
Which two actions should the project manager take? (Choose 2)

الخيارات

  • A Divide the team to continue working on both the presentation and the project work.
  • B Attempt to complete the presentation work alone so that the timeline is not negatively impacted.
  • C Determine a new target completion date for the project based on the redirection of the team.
  • D Request the CEO to assign some of the functional team members to work on the presentation.
  • E Ask the team to work overtime to make up the time lost by supporting the technology summit.