A department lead requested additional items be included in the project during the execution phase. Their acceptance is mandatory before the project can be closed.
What should the project manager do first?

الخيارات

  • A Find a way to accommodate the requested additions.
  • B Initiate a change request for the additional scope.
  • C Schedule a meeting to gain better understanding.
  • D Politely refuse the request stating the project baselines.