A project manager has developed a communications management plan. A junior team member asks why they are duplicating efforts by producing different versions of the same newsletter.
How should the project manager respond?

الخيارات

  • A Explain that to prepare for all situations and as part of risk mitigation, many different newsletters are created just in case they are needed.
  • B Explain that customized newsletters are part of the organizational culture and that following this step-by-step process is of utmost importance.
  • C Explain that each individual newsletter is based on specific categories of communication for the intended audience.
  • D Explain that each stakeholder expects a different customized newsletter, ensuring it complies to all of their requirements.