السؤال 624 من 874

كل الأسئلة

During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.
What should the project manager ask the team to do next?

الخيارات

  • A Execute the smaller estimated activities.
  • B Break down the larger activities into smaller ones.
  • C Negotiate the estimation so it gets smaller.
  • D Resize the story points.