اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 620 من 874

كل الأسئلة

A software delivery project is in the execution phase. The project team has identified a need for an additional server as the software requires more data storage space than planned for. Without the additional server, the project delivery cannot continue.
What should the project manager do?

الخيارات

  • A Raise a change request and obtain approval from the project owner.
  • B Use the project budget and procure a new server before raising a change request.
  • C Apply contingency reserves to procure a server that fits the requirement.
  • D Request that the requirement is funded with the business operational expenses.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.