A project feature from the development team was rejected due to low quality. Over the past few weeks, the testing team has become concerned because the development team has not yet responded to the rejection. As a result, the testing team has escalated the conflict to the project manager.
What should the project manager do?

الخيارات

  • A Reassure all team members that the development team will fix the issue.
  • B Initiate an improvement plan for the development team to follow.
  • C Remove the development team's rejected feature from the backlog.
  • D Evaluate the context for the conflict with the development team.