A project manager is creating the quality management plan for deliverables with very precise requirements. The project manager is uncertain about how to create quality standards so the suppliers can show conformity when delivering the product.
Which two actions should the project manager take first? (Choose 2)

الخيارات

  • A Add a conformity team member to inspect each deliverable upon receipt from the supplier.
  • B Review the conformity management plan to ensure the requirements are clearly defined.
  • C Evaluate industry standards of similar products to determine which apply to this project.
  • D Reference the quality management plans from old projects to determine if they apply to these deliverables.
  • E Add a conformity team member to inspect each deliverable upon receipt from the supplier.
  • F Review the conformity management plan to ensure the requirements are clearly defined.
  • G Evaluate industry standards of similar products to determine which apply to this project.
  • H Reference the quality management plans from old projects to determine if they apply to these deliverables.
  • I Ask the suppliers to create a statement of conformity when the product is delivered.