During planning, a virtual project team agreed to the project reporting structure and established a meeting cadence that fits multiple time zones. One month into execution, the project manager notices that certain members are disengaged during project meetings.
What should the project manager do to resolve this issue?

الخيارات

  • A Distribute the meeting agenda and objectives the day before the project meetings.
  • B Work with the team to review the effectiveness of the agreed project practices.
  • C Review the project reporting structure to clarify the project objectives.
  • D Set up follow-up sessions on all action items for team members.