A project team is working together for the first time. During the first sprint, the project manager was asked to solve a prioritization conflict between the scrum master and the product owner related to a feature requested by an important customer.
How should the project manager resolve this conflict?

الخيارات

  • A Emphasize that the scrum master has the responsibility to conduct the sprint planning.ج
  • B Contact the customer to understand the request in order to make a decision.
  • C Schedule a meeting with the scrum master and product owner.
  • D Refer to the roles and responsibilities for the agile team.