A project team has difficulty understanding the relationship between functional requirements and their associated benefit to the business stakeholders. How should the project manager improve the team's understanding?

الخيارات

  • A Engage with the project sponsor and ensure the product backlog is correct and up to date.
  • B Invite all stakeholders to progress meetings to avoid ambiguity.
  • C Involve team members in stakeholder analysis and engagement.
  • D Ensure team members have access to a well-written requirements traceability matrix.