A new project manager took over a project that has been ongoing for a while. Some project team members are not clear on when the project will end and feel the project has already transitioned into business as usual.
What should the new project manager do first?

الخيارات

  • A Meet with the team and gather their input on the completion rate.
  • B Transition to an agile delivery so project closure will be faster.
  • C Consult the sponsor and secure approval to complete the project.
  • D Revisit the timelines of the deliverables and the project.