A new project team consists of team members from different departments who have varying levels of experience and different areas of expertise. Which three approaches should the project manager take in order to facilitate knowledge sharing? (Choose 3)

الخيارات

  • A Identify external subject matter experts (SMEs) and plan training sessions to conduct knowledge transfer.
  • B Assess the gaps and assign an expert resource for respective areas of knowledge.
  • C Arrange a daily learning session for project team members during lunch to facilitate knowledge transfer.
  • D Schedule shadowing sessions among team members to facilitate team learning.
  • E Allow each team member time in the retrospective sessions to share a little bit about their role and areas of knowledge.