A project team is working on a company restructure that involves team member rotation. There is a concern about how to execute the project within the schedule based on all of the new team members.
What should the project manager do?

الخيارات

  • A Set up a team alignment session to discuss the remaining work and contract with the team.
  • B Advise the new team that the schedule cannot be changed and encourage them to complete the project.
  • C Ask the team to analyze the impact and develop a new schedule for a project change request.
  • D Discuss the issue with the project sponsor and advise that the project will probably be delayed.