A company was acquired, and the new company management asked the project manager to begin using a specific set of metrics immediately to measure team performance. The project manager is working on a predictive project and thinks this request will distract the team and delay the project.
What should the project manager do first?

الخيارات

  • A Support the required metrics during the next project phase.
  • B Assess and analyze the impact of using these metrics.
  • C Involve the team in reviewing the proposed metrics.
  • D Request an extension to implement the new metrics.