A project manager has been assigned to lead a project with limited funding and resources. During the requirements brainstorming session, several stakeholders request a long list of requirements for a new project, which exceeds the budget.
What should the project manager do first?

الخيارات

  • A Reach out to the sponsor and request additional budget and capacity in order to complete the project.
  • B Meet with the sponsor to obtain their feedback regarding critical requirements in the view of senior management.
  • C Review the requirements and determine which of them can be removed, then advise the stakeholders of the changes.
  • D Host a requirements workshop and ask the stakeholders to prioritize the requirements based on critical needs.