A project manager was suddenly asked to take over an ongoing project without any handover. During the first meeting, the project sponsor raised concerns about whether the project was on track to deliver the intended benefits.
What should the new project manager do first?

الخيارات

  • A Initiate a rebaselining of the project based on the project sponsor’s concerns.
  • B Review the business case to gather information about the project.
  • C Meet with the project stakeholders to understand the project sponsor’s concerns.
  • D Discuss the items in the requirements register with the project team.