A project manager is working on a project to transform the service delivery model in the organization. As part of the scope, this project includes diverse elements as part of the scope that have been well defined by the product owner. The team has expressed that the scope is not clearly defined.
How should the project manager address this situation?

الخيارات

  • A Ask the product owner to clarify the project’s vision with the team.
  • B Ask the team members to focus only on their assignments.
  • C Distribute the release plan among the team members.
  • D Meet with the product owner to validate the backlog prioritization.