اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 555 من 874

كل الأسئلة

A project for a financial organization is in the proposal phase for the selection of a software tool. There have been conflicting opinions on the software that was ranked in the selection. After analyzing the issue, the project manager realizes that two out of the eight teams have concerns about the tool’s scalability to support their business needs.
How should the project manager resolve this conflict and reach a consensus?

الخيارات

  • A Communicate to the two teams that the tool has won per the selection process and they need to accept the outcome.
  • B Escalate this to senior management and ensure that the team’s acceptance is achieved.
  • C Discuss the outcome of the proposal process and the ranking, then influence the team for acceptance.
  • D Ignore the conflict as the tool is selected per the proposal guidelines and the project is complete.