An organization is altering their schedule, and the project team is now expected to be in the office together once a week. Despite everyone being dedicated to the project, the team members all follow their functional teams' schedules, which differ from one another.
How should the project manager address this situation?

الخيارات

  • A Look into the option of changing the status of all team members to being fully remote.
  • B Work with the team to determine if the in-person project day is required.
  • C Look into changing the company’s policy from 1 day to 2 days on-site.
  • D Work with the functional managers and get an exception for the team members.