During the testing phase of a project, the project manager is made aware that components delivered from a specific vendor have defects. However, the vendor refuses to fix the defects because it will incur additional costs for them.
What should the project manager do next?

الخيارات

  • A Request cancellation of the contract with the vendor.
  • B Review the acceptance criteria defined with the vendor.
  • C Ask the vendor for revised timelines and cost needs.
  • D Communicate with the vendor for contract changes.