An information technology project manager works at an insurance company and is assigned to an infrastructure upgrade project. During the execution phase, a stakeholder approaches the project manager and informs them that a deliverable is not meeting the quality requirements.
What should the project manager do first?

الخيارات

  • A Acknowledge the stakeholder's concerns and work to correct the deliverable.
  • B Compare the stakeholder's assertion to the metrics in the quality report.
  • C Update the risk register with information on the noncompliant deliverable.
  • D Ask the project sponsor for additional funding for improved quality outcomes.