During the second sprint for a project, a project manager realizes some user stories are no longer valuable for the business. What should the project manager do?

الخيارات

  • A Schedule a post-sprint retrospective meeting to analyze the changes in the user stories.
  • B Schedule a meeting with the project sponsor to validate new user stories.
  • C Stop the sprint and schedule a backlog refinement meeting.
  • D Meet with the change control board (CCB) to approve changes.