During a progress meeting, the project manager notes that a key stakeholder is expecting benefits from the project that have not been planned. The stakeholder misinterpreted the benefits document that was shared, and the project manager is afraid this may negatively impact the project's success.
What should the project manager do?

الخيارات

  • A Resend the benefits document and highlight the misunderstood point.
  • B Engage with the stakeholders to ensure common understanding of benefits.
  • C Revisit the benefits management plan and include additional information.
  • D Document the benefits and escalate the situation to the project sponsor.