اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 520 من 874

كل الأسئلة

A project manager is leading a software development team to upgrade a banking software. During a sprint review, the product owner suggested a small addition to the process that might necessitate a change to the sprint.
What should the project manager do?

الخيارات

  • A Evaluate the product owner's proposed change alone and consult the project sponsor for approval.
  • B Accept the product owner's suggested change and notify the project sponsor of the acceptance.
  • C Review the proposed change with the team and consult the project sponsor for approval.
  • D Submit the proposed change to the change control board (CCB) to evaluate and approve.

النقاشات