A client is upset because of a change to the target date provided by the project manager. The sales team had previously provided a different target date when signing the statement of work (SOW).
What should the project manager do to address the situation with the client?

الخيارات

  • A Determine which of the assumptions the sales team used when creating the SOW proved to be invalid, causing impact to the target date.
  • B Request authorization for additional resources to work on the project and increase likelihood that the client’s desired target date is achieved.
  • C Negotiate a reduced scope and revise the SOW to increase likelihood that the client’s desired target date is achieved.
  • D Explain that a better understanding of the work and dependencies has resulted in a target date that is different from what was conveyed in the SOW.