A project manager is trying to define a project time line despite having incomplete and ambiguous information on requirements and regulations. What should the project manager do to finish planning?

الخيارات

  • A Perform an assumption and constraint analysis to provide more opportunities and remove limiting factors.
  • B Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.
  • C Execute a root cause analysis to discover the underlying factors that might lead to risks and issues.
  • D Review project documents to identify and eliminate uncertainties and inconsistencies.