اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 510 من 874

كل الأسئلة

A project is impacting several business units with different expectations and priorities. The project manager leading this project is meeting every month with each of these groups individually. During these meetings, each group has expressed dissatisfaction with the project and uses every opportunity to replace other groups' priorities with their own.
What should the project manager do to address these challenges?

الخيارات

  • A Escalate the priorities of all the groups to the project sponsor and ask them to facilitate the process.
  • B Establish consensus on project priorities by meeting with all the groups together.
  • C Develop a project schedule that accommodates all requirements from all groups.
  • D Meet with each group separately to avoid confrontation and send meeting notes at the end of each meeting.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.