A project manager works for an IT consulting firm that has submitted a bid during the request for proposal (RFP) process for a contract that focuses on data center migration and optimization. However, the consulting firm has little experience in data center optimization.
What should the project manager do?

الخيارات

  • A Outsource the data center optimization work to a vendor.
  • B Request a budget to build this competency among project team members.
  • C Partner with a company that is an expert in this area.
  • D Send the team to a data center optimization training workshop.