اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 506 من 874

كل الأسئلة

During a discovery phase, a project manager coordinated a brainstorming event to determine the best strategy to meet the product release date. After the project overview, the subject matter expert (SME) remained quiet during the call.
What should the project manager do next?

الخيارات

  • A Create a strategy based on the project manager's experience and get approval during the call.
  • B Pose direct questions to the participants based on their area of expertise to start engaging them in the conversation.
  • C Review the roles and responsibilities during the call to determine who is accountable for the strategy.
  • D Cancel the meeting if team members do not have the skills to suggest a strategy.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.