A project management office (PMO) is following the execution of an organization’s critical project. Some of the project phases are experiencing serious delays due to an international supply chain crisis. Project team members suggested revisiting the planned project phases to maintain the project’s value delivery.
What should the project manager do?

الخيارات

  • A Develop a contingency plan and seek alternative suppliers.
  • B Schedule a meeting with the project sponsor to report and discuss the issue.
  • C Assess and consolidate project phases and update the project management plan.
  • D Update the project schedule in response to the external crisis.