A project manager is working on a project with a global project team. Some team members are not happy with the times of the scheduled project review meetings and are not joining the meetings. This lack of team participation is leading to improper project status reporting.
What should the project manager do?

الخيارات

  • A Discuss with the functional managers and adjust the schedule.
  • B Discuss with the project sponsor and arrange the meeting times.
  • C Discuss the meetings agenda with the project team members.
  • D Discuss with the invited team members and adjust the schedule.